Why Anan Chose Afula and Tzora
The question is not where land is available or affordable. It is where the hard requirements of large-scaleAI infrastructure - power, grid access, security, and connectivity - can be met at scale and on a deliverabletimeline. At Anan, that analysis led us to two sites: Afula in northern Israel, and Tzora in the Judeanfoothills between Jerusalem and Tel Aviv.
Afula: Power First
Power availability is the primary constraint in data centre development today. In a market where dedicatedsubstations and grid connections can take years to secure, the ability to contract power before breakingground is a critical execution advantage.
At the Afula site, Anan secured its electricity contracts, dedicated substation, and redundant power feedsbefore construction began. That sequencing - power first, construction second - is what allows us tocommit to delivery timelines that global AI operators can rely on.
Northern Israel's grid infrastructure, developed over decades to serve its industrial zones, offered availablehigh-voltage capacity at the scale required for a 64MW facility with a development pathway to 100MW.
Afula campus specifications:
- 30,000 sqm across one underground floor and three above-ground storeys
- Advanced liquid cooling supporting rack densities of 60kW and above
- Dedicated substations with redundant power feeds
- Fortification level C+, aligned with Israeli defence and seismic standards
- Total capacity pathway to 100MW
Tzora: The Centre of Gravity Between Two Cities
Israel's digital economy is concentrated around two poles: Tel Aviv, the commercial and technology hub,and Jerusalem, home to government, defence, and major public-sector institutions. The Tzora site sitsbetween them, less than 30 minutes from both cities.
For customers building hybrid cloud architectures or requiring sovereign, low-latency compute close toJerusalem-based operations, that geographic positioning is directly relevant. The site is approximately onekilometre from existing hyperscaler infrastructure in the area, enabling low-latency interconnection forworkloads that move between private and cloud environments.
Tzora facility specifications:
- Built entirely underground
- 32MVA of capacity - the maximum permitted at a single site in Israel
- N+N redundancy across all systems
- Protection level exceeding standard C+ requirements
- Highly efficient water-cooled chiller system targeting a PUE of 1.4
- 24,000 sqm of purpose-built AI-ready infrastructure
Israel's Regulatory Tailwind
In February 2026, the Israeli government approved a resolution defining data centres as nationalinfrastructure and introduced a fast-track planning mechanism for AI-ready facilities above 50MW. BothAnan sites are positioned to benefit directly from this framework.
The deliberate geographic distribution of our portfolio - one site in the north, one in the centre - reflects abroader national infrastructure logic. As Israel's total data centre pipeline grows toward 1GW of plannedcapacity,1 the concentration of existing facilities around Tel Aviv creates both congestion and opportunityfor well-positioned developments outside that corridor.
Both sites have power secured, permits granted, and construction underway -achieved before anchor customer commitments at either location.
1 Energy and Infrastructure Minister Eli Cohen stated that "planning and establishment procedures have begun for data centers with acapacity of 1 Giga" during the presentation of Government Resolution No. 3907, "Promoting the Construction of Advanced Data Centers toStrengthen Israel's Leadership in the Field of Artificial Intelligence" (22 February 2026).